IC 13-18-26-6 — Completion, periodic revision, and public disclosure of analysis and plans
Chapter 26. Permit and Permit Application Conditions for Water and Wastewater Treatment Plants
Section text
Sec. 6. (a) The analyses and plans described in sections 3, 4, and 5 of this chapter must be: (1) complete under the requirements of this chapter at the time an application for a permit described in section 1(a) or 1(b) of this chapter is submitted; (2) reviewed and revised at least once every five (5) years, for as long as the permit holder operates the water treatment plant or wastewater treatment plant; and (3) except for customer specific data, including information excluded from public access under IC 5-14-3-4(a), or for a cybersecurity plan required under section 5 of this chapter, made publicly available. (b) A certification that the analyses and plans described in sections 3, 4, and 5 of this chapter are complete under the requirements of this chapter must be submitted to the department: (1) under section 2 of this chapter at the time an application for a permit described in section 1(a) or 1(b) of this chapter is submitted; and (2) at least once every five (5) years after an application for a permit described in section 1(a) or 1(b) of this chapter is submitted, when the analysis and plans are reviewed and revised. (c) A certification submitted to the department under this chapter must be notarized.
As added by P.L.126-2018, SEC.6. Amended by P.L.15-2019, SEC.14.
Source: official publisher (2026 edition)